Dunlap Hall Renovations Delayed Until At Least 2016

DH-Newsbrief
By Joanna Uriostegui

Unforeseen complications pushed back the opening of the college’s largest building until at least 2016, district officials said.

“The existing Dunlap Hall roof was beyond its useful life and leaking. It is best to complete the roof replacement while the building is still unoccupied,” said Darryl Taylor, director of facility planning.

The work delayed the installation of satellite, cable and other communications devices, which are housed on the roof.

The four-story Dunlap Hall, located at the southeast side of Santa Ana College, was closed for repairs last year. Construction crews are working to bring the 40-year-old building up to code, such as making its bathrooms more accessible to disabled and handicapped students.

The renovation was projected to cost $18.7 million, which includes contractor fees, material testing, inspections, and architect and engineering services.

Previous Story

Getting To Know: Athletic Counselor Frank Gonzales

Next Story

District Officials Address Concerns Surrounding Decision to Re-Arm Safety Officers

Latest from Blog

In Photos: Gas Crisis (Here we go again)

In the early 1970s, and again in 1979, gasoline shortages triggered by conflicts in oil producing regions resulted in gas rationing and long lines locally. My brother and I were in our

The beauty of Santa Barbara

I transferred to the University of California Santa Barbara in 2017 and graduated three years later during the height of the Covid-19 pandemic. Over that period I learned more about myself outside
Go toTop

Don't Miss

A collage of construction photos with excavators in dirt lots

High-end apartments, restaurants, a swanky hotel: exploring Santa Ana’s controversial $4 billion development

Photos by Dylan Burch, Giovanni Castro and Christopher Michael Driving

Improvements to be made to facilities this school year

Filling cracks on the roof of the Technical Arts Building.