By John Olivares After an 18-month makeover, Dunlap Hall is back in business. Building upgrades include new steel guardrails, upgraded elevators that do not require key cards and a staircase entry closer
By John Olivares Dunlap Hall is scheduled to reopen in spring of next year following a one-and-a-half year completion delay due to roof leaks. Construction crews are working to renovate and replace
By Joanna Uriostegui Unforeseen complications pushed back the opening of the college’s largest building until at least 2016, district officials said. “The existing Dunlap Hall roof was beyond its useful life and
By: Katie Porter Construction plans for Dunlap Hall won’t interrupt classes this spring, administrators said. The 40-year-old building will be renovated with updates to the stairs, restrooms and elevator, starting in April,